Today on I-94: check 511mn.org
Current
Work operations suspended for winter season
Off-road work and periodic lane closures to occur anytime on this project.
- I-94 construction on mainline resumes in full force spring 2025
Wright County
Off-road work and periodic lane closures to occur anytime on this project.
Improve and expand I-94 to six lanes, three in each direction, to close the gap between Albertville and Monticello, Wright County. All six lanes to open late fall 2026.
Watch a quick clip to learn about this future I-94 project between Albertville and Monticello.
Source: MnDOT Vimeo Channel
Periodic lane closures and off-road work to occur at anytime on this project.
Dates | Work | Impacts |
COMPLETE July 22 - Oct. 25, 2024 |
Prepare work areas, includes road widening, temporary median crossovers |
All lanes open for 2024-2025 snow and ice season |
Spring - Fall 2025 | Construct westbound, includes noisewalls, WB Co. Rd. 19 bridge, Co. Rd. 18 ramps | Open to two lanes, both directions: traffic on eastbound side; expect changes to access |
Spring - Fall 2026 | Construct eastbound, includes noisewalls, Co. Rd. 18 ramps | Open to two lanes, both directions: traffic on westbound side of interstate; expect changes to access |
Spring - summer 2027 | Wrap up any work | Periodic lane closures |
When complete in 2026, the westbound lanes in the MnROAD area from Albertville to Monticello will be as they are today—except three lanes. The future test section along westbound I-94, will be for truck traffic only. Drivers will use a entrance ramp from westbound I-94, drive on the test section and use a exit ramp back onto westbound. Signs will signify truckers a road test is in operation and they need to exit ahead. More details to become available when known.
Schedule is subject to change.