Hwy 14

Tracy to Revere

Traffic impacts

Hwy 14 from Tracy to Revere
Overview - detour will allow access to Walnut Grove when construction begins.

Current traffic impacts

  • Detour began Monday, May 13, 2019.
  • Work crews will provide access to homes and businesses located along the construction route
  • No through traffic

Project updates

  • June 21, 2019:
  • Cold-in-place recycle (CIR) operations completed.
  • First lift of asphalt pavement has been placed from Revere to bridge just west of Walnut Grove, operations will continue west to Tracy.
  • Slope repair work near the Tracy Golf Course began June 17; sheet pile is installed and slope material and riprap being placed.
  • Additionial milling operations for tapers in Tracy and Walnut Grove are in to prep for the second lift.
  • Shouldering operations have begun and will work east from the bridge to Revere.

Sign up for email updates on this project

About this project

Project summary

  • Pavement resurfacing and chip seal
  • Culvert repair
  • Extension of right-turn lane and right-run lane at intersection of CR 80
  • Extend radius near elevator
  • Upgrade sidewalks, pedestrian ramps and adjacent driveways in Walnut Grove to meet modern ADA standards
  • Update guardrail

Project cost

  • $5.1 million

Contractor