Hwy 91

Nobles/Murray County line to Russell

About this project

Traffic impacts

  • Construction begins June 17, 2019
  • Lane closures during pavement resurfacing
  • Detour 1 is projected to run from July 15 - August 27, 2019 (Hwy 91 will be open to local traffic only)
  • Detour 2 is projected to run from August 27 - September 17, 2019 (Hwy 91 will be open to local traffic only)
  • See project Map A with detours below
  • District 7 map (Map B) shows detour information for Hwy 91 south of Lake Wilson

Summary of work

  • Resurfacing 45 miles of Highway 91 from the Murray/Nobles county line to Russell in Lyon County
  • Replacement of four bridges
  • Repair and clean culverts
  • Replace culverts that cannot be repaired
  • Sidewalk and pedestrian improvements (ADA improvements) in Lake Wilson
  • District 7 is resurfacing Hwy 91 from the northern Nobles county line (CR 72) to the southern Adrian city limits. Find information on this related project also scheduled for construction in 2019-2020.