About this project
Crews have replaced the bridge and reconstructed the interchange at Hwy 169 and Co. Rd. 9 (Rockford Rd./42nd Ave.) between New Hope and Plymouth. We also put in accessible sidewalks for pedestrians and bicyclists during construction.
Summary of work
- Replace the old bridge with a new, wider bridge
- Rebuilding the interchange from a full cloverleaf into a folded diamond layout
- Adding additional turn lanes and ramp lanes for drivers
- Adding new signal systems
- Replacing existing signals at Nathan Ln. and Gettysburg Ave.
- Adding new pedestrian and bike trails on both sides of Rockford Rd. for better and safer connection for Plymouth and New Hope pedestrians and bicyclists