Minnesota Department of Transportation

511 Travel Info

Highway 5/East 7th Street and Highway 61/Arcade Street

St. Paul and Maplewood

Join us for Office Hours on Thu, May 15. Community members are invited to stop by to ask questions about the East 7th St. and Arcade St. project. For more information, visit the meetings webpage.

This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.

Traffic impacts

East 7th Street and Arcade Street in Saint Paul and Maplewood project location map

East 7th St. and Arcade St. project area map

View full-size map

All traffic impacts are tentative and weather dependent. Local access to residences and businesses will be maintained. Access and parking for businesses are available using side streets. Intermittent parking may be available on Arcade St. between Wheelock Pkwy. and Maryland Ave. and Magnolia Ave. and York Ave. depending on specific work being done.

Drivers can expect intermittent intersection closures throughout the project area; however, no two consecutive intersections will be closed at the same time. People walking and rolling can expect sidewalks and boulevards to be removed and reconstructed during the project. People walking, rolling and driving should follow the posted detours for any closures.

Current

Road closures

March 31 through early summer

Upcoming

Information about upcoming traffic impacts will be posted as details become available.

Road closures

Mon, May 19 through late summer

Construction timeline

Arcade Street in Saint Paul and Maplewood construction timeline map

Arcade St. construction timeline map

View full-size map

  • Spring through fall 2025: Arcade St. between East 7th St. and Roselawn Ave.
    • Stage 1A (Arcade St. between Frost Ave. and Wheelock Pkwy.): Late March through early summer
    • Stage 1B (Arcade St. between Wheelock Pkwy. and Maryland Ave.): Late May through late summer
    • Stage 2A (Arcade St. between Maryland Ave. and Magnolia Ave.): Late March through mid-summer
    • Stage 2B (Arcade St. between Magnolia Ave. and Case Ave.): Mid-summer through early fall
    • Stage 2C (Arcade St. between Case Ave. and Neid Ln.): Early fall through late fall
  • Spring through fall 2026: East 7th St. between I-94 and Minnehaha Ave.

Construction activities

Utility work (water, electrical, gas, etc.) will occur intermittently throughout all parts of the project area, not just where road construction is happening.

Arcade St. between Frost Ave. and Wheelock Pkwy.

Upcoming activities:
  • Week of May 19, crews will pour concrete for new sidewalks.
  • Starting week of May 19, crews will install stormwater sewer at the Wheelock Pkwy. and Arcade St. intersection.

Arcade St. between Wheelock Pkwy. and Maryland Ave.

Upcoming activities:
  • On May 22, crews will start removals of the roadway on Arcade St. between Wheelock Pkwy. and Maryland Ave.

Arcade St. between Maryland Ave. and York Ave.

Ongoing activities:
  • Crews continue watermain replacements
  • Crews continue utility work through early summer

About this project

In March 2025, we began the two-year reconstruction project along East 7th St., and Arcade St. between I-94 in St. Paul and Roselawn Ave. in Maplewood. Construction is underway on Arcade St. for the 2025 construction season. Construction on East 7th St. will occur during the 2026 construction season. When complete, the new roadway will improve traffic flow, decrease traffic delays and improve safety on the road. Construction is expected to be completed in fall 2026.

Summary of work

  • Resurfacing the road
  • Repairing sidewalks
  • Updating sidewalk curb ramps and driveways
  • Updating and improving pedestrian lighting
  • Updating and improving traffic signals
  • Updating and improving bus stops