About this project
Summary of MnDOT work

- MnDOT is reconstructing Highway 19/College Drive from 700 ft west of Marlene St through the intersection of Bruce Street in the City of Marshall.
- The City of Marshall is replacing sanitary sewer and water main utilities.
- A single-lane roundabout will be constructed at the intersection of Highway 19/College Drive, Country Club Drive, and South 2nd Street.
- An EV Charging Station will be installed in the Avera parking lot.
- Sidewalk improvements will be made along the project area to improve accessibility.
- Several traffic control changes throughout the route will be made to enhance safety.
- A bike lane will be striped from Marlene St. to just west of Fairgrounds Rd.
- Trees will be replanted in the fall of 2026(PDF). Tree selections can be viewed here(PDF), please note, these are subject to change.
Project update: June 4, 2026
Work zone: Main Street to Liberty Park Bridge
- Concrete paving has been completed from Lyon Street to Redwood Street and Redwood Street to Marshall Street. Crews are working on paving the Lyon Street crossing.
- ADA components continued to be poured at intersections. These include landings, ramps and truncated domes which are textured surfaces used as a warning for people who are blind or have low vision.
- Concrete sidewalks continue to be installed.
- Bridge work continues on Liberty Park Bridge.
- Underground electrical work continues for street lighting.
Work zone: Main Street/ East College Drive intersection (Hwy 19/Hwy 59/Hwy 68)
- Curb and gutter installation have been completed.
- Signal system foundations are being formed and poured.
- Signal system electrical, footing, and underground work is underway.
- Concrete paving is scheduled to begin June 4 in the intersection.
- Signal loops are being installed. A signal loop is a sensor buried in the pavement that tells a traffic light when vehicles are present.
Work zone: Bruce Street/ Highway 19 intersection
- Sanitary sewer installation is complete.
- Storm sewer installation is underway.
Work zone: Legion Field Bridge to Main St.
- Intermittent finishing work will be taking place.
Work planned for next week
*All proposed work is weather permitting
Main Street to Liberty Park Bridge
- Concrete paving will continue.
- ADA work will continue.
- Sidewalk work will continue.
- Street lighting underground electrical work will continue.
- Street lighting foundation work and pole setting will begin.
Main Street/ East College Drive intersection
- Concrete paving will continue.
- ADA work will begin.
- Sidewalk work will begin.
- Signal system foundation work is scheduled to be completed. Cure time is required before signal poles can be installed on the foundations.
- Signal system loops installation is scheduled to be completed.
- Signal system controller cabinet is scheduled to be installed.
Bruce Street/ Highway 19 intersection
- Watermain installation is scheduled to begin.
- Storm sewer installation is scheduled to be completed.
Legion Field Bridge to Main Street on Highway 19 (year 1 project area)
- Maintenance work on installed items.
Traffic access and impacts
- The Bruce St. / East College Dr. intersection is closed.
- Businesses are open and can be accessed from either Hwy 19 west from North 3rd Street or Highway 19 east from Hwy 23.
- Access across the intersection is closed.
- Main St. to Liberty Park Bridge on Hwy 19 is closed.
- Traffic must use the detour on CR 7 and Hwy 23.
- Main Street/Hwy 19 intersection is closed.
- Traffic should use CR 33 and Hwy 23.
- West Lyon Street and West Marshall Street are closed at Highway 19.
- Alleys between West Lyon Street and West Redwood Street, and between West Redwood Street and West Marshall Street are closed at Highway 19.
- West Redwood Street will be open to cross at Hwy 19.
- Hwy 19 is open to local traffic from North 3rd Street to Bruce Street.
- Businesses within the work zone remain open.
- Addison Public Parking Lot is open.
- Please watch for pedestrians.
2025: Stages 1-4
2026: Stages 5-7


