MnDOT is planning to resurface two bridges on Hwy 23, north of Marshall crossing the Redwood River and Threemile Creek near Green Valley
Summary of work
- Resurface bridge decks
- Replace approach panels
- Replace guardrails
Traffic impacts
- A detour is in place for the duration of this project.
- Traffic will be routed to Hwy 19 and CR 9.
Project updates
May 30, 2025
- Crews repaired the decks and formed up the new bridge joints.
- They're also working on the bridge rails, forming the new extensions.
- Next week they will work on the sills within the bridge approach panel areas with a goal to pour the new approach panels by the end of the week.